Example

SWMS Example: Safe Work Method Statement

A Safe Work Method Statement (SWMS) is required for high-risk construction work in Australia. This example shows a completed SWMS for a pump replacement task that you can adapt.

7 min readUpdated July 2026

What is a SWMS?

A Safe Work Method Statement (SWMS) is a document that outlines the high-risk construction work being performed, the hazards and risks associated with each step, and the control measures to be implemented. In Australia, a SWMS is legally required for high-risk construction work as defined by the Work Health and Safety Regulations.

Completed Example: Pump Replacement

Business Details

Business name: ABC Maintenance Services Pty Ltd

ABN: 12 345 678 901

Contact: John Smith, 0412 345 678

Principal contractor: XYZ Manufacturing Pty Ltd

Work site: Plant Room 1, 123 Industrial Drive

High-Risk Work Description

Replacement of centrifugal pump P-101 in the boiler house. Work involves electrical isolation, mechanical disconnection, lifting operations, and hot work (welding of the base plate).

Step-by-Step Method

Step 1: Preparation and Isolation

Hazards: Electrical energy, pressurised water, hot surfaces

Controls: Complete LOTO on pump motor (main isolator #MCC-101). Close suction and discharge isolation valves. Open drain valve and verify zero pressure. Allow pump to cool below 40°C. Verify isolation by attempting to start pump.

Responsible: Licensed electrician + mechanical technician

Step 2: Disconnection of Piping

Hazards: Residual water, manual handling, slips

Controls: Place spill tray under flanges. Wear chemical-resistant gloves and safety glasses. Use mechanical lifting aid for heavy components. Clean up spills immediately with absorbent material.

Responsible: Mechanical technician

Step 3: Removal of Old Pump

Hazards: Manual handling, crushing, dropped object

Controls: Use chain block rated for 500kg (pump weight 200kg). Inspect lifting gear before use. Clear exclusion zone — 2m radius. Two-person lift. Wear safety boots and gloves.

Responsible: Rigger + mechanical technician

Step 4: Hot Work — Welding Base Plate

Hazards: Fire, burns, fumes, UV radiation

Controls: Hot work permit obtained. Clear 10m radius of combustibles. Fire watch assigned (dedicated person). Fire extinguisher (CO₂) on standby. Gas test completed (below 10% LEL). Welder wears full PPE — welding helmet, leather gloves, fire-resistant clothing. Mechanical ventilation for fume extraction.

Responsible: Certified welder + fire watch

Step 5: Installation of New Pump

Hazards: Manual handling, crushing, misalignment

Controls: Use chain block. Laser-align coupling to within 0.05mm. Torque flange bolts to specification. Install new gaskets.

Responsible: Mechanical technician

Step 6: Reconnection and Commissioning

Hazards: Re-energising, leaks, pressure

Controls: Remove locks and tags (each worker removes own). Open suction valve first. Start pump with discharge valve cracked. Check for leaks. Monitor vibration and temperature for 30 minutes.

Responsible: Mechanical technician + electrician

Sign-off

Prepared by: John Smith (Site Supervisor) Date: 12/07/2026

Reviewed by: Jane Doe (HSE Manager) Date: 12/07/2026

Worker acknowledgment: All workers have read and understood this SWMS.

SWMS vs JSA — What's the Difference?

CharacteristicSWMSJSA
Legal requirementLegally required for high-risk construction work in AustraliaNot legally required but best practice
When usedConstruction work with high-risk activitiesAny maintenance or operational task
Detail levelDetailed, formal, site-specificCan be simpler, task-specific
RetentionMust be retained for specified periodFiled with work order

Pro tip: A well-written SWMS or JSA should be specific enough that a qualified person who has never done the task before could follow it safely. If it's too generic, it's not providing the safety value it should.