Guide

Hot Work Permit: Requirements & Procedure

Hot work — welding, cutting, grinding — is a leading cause of industrial fires. This guide covers the hot work permit system, fire prevention measures, and the fire watch requirements that prevent disasters.

7 min readUpdated July 2026

Fire Risk

Hot work is one of the leading causes of industrial fires. Sparks can travel 10+ metres and smoulder for hours before igniting. A properly executed hot work permit system prevents these fires.

What is Hot Work?

Hot work includes any activity that generates heat, sparks, or open flame:

  • Welding (arc, MIG, TIG, gas)
  • Cutting (oxy-acetylene, plasma, grinding)
  • Grinding (angle grinder, disc grinder)
  • Soldering and brazing
  • Using open flame (torches, heat guns)
  • Drilling or chipping that could create sparks (in hazardous areas)

Pre-Work Checklist

☐ Hot work permit completed and authorised

☐ Area within 10 metres cleared of combustibles (or covered with fire blankets)

☐ Floor drains within 10 metres covered — sparks can enter drains and ignite flammable residues

☐ Wall and floor openings within 10 metres covered — sparks can travel through openings

☐ Combustible materials that cannot be removed are protected with fire-resistant blankets

☐ Fire extinguisher (appropriate type) available within 3 metres of the work

☐ Fire watch assigned — a dedicated person whose only job is to watch for fire

☐ Gas testing completed — atmosphere checked for flammable gases (below 10% LEL) before work starts

☐ Ventilation adequate — ensure fumes are extracted

☐ All other work in the area stopped — no simultaneous hot work and flammable work

☐ Adjacent areas checked — sparks can travel through walls, ducts, and openings

Fire Watch Requirements

  • A fire watch must be present during ALL hot work and for at least 30 minutes after work is completed (some jurisdictions require 1 hour)
  • The fire watch must have NO other duties — their only job is to watch for fire
  • The fire watch must be trained in using fire extinguishers
  • The fire watch must have a means of communication (radio, phone) to call for help
  • If the work is in a high-risk area (process plant with flammable materials), consider continuous monitoring for several hours after work
  • If the hot work is in a concealed space (above a ceiling, inside a wall), the fire watch must continue for at least 2 hours after work is completed

Alternative: Cold Work

Before issuing a hot work permit, consider whether cold work methods could be used instead:

  • Mechanical cutting (saw, pipe cutter) instead of oxy cutting
  • Mechanical bolting instead of welding
  • Epoxy bonding instead of welding
  • Cold repair composites for pipe repair
  • If cold work is feasible, it should always be preferred over hot work